Project: Prince’s Island
Pedestrian Bridge Deck
Resurfacing
Owner: City of Calgary
Location: Calgary Downtown – Over
The Bow River
The Problem:
Client was experiencing rust blisters
and loss of traction on existing bridge
deck coating. They required a
replacement procedure that would
allow pedestrian traffic to continue,
and preserve the environment and
waterway below.


Service / Product Provided: One
half, and 200 linear feet of the bridge
was 100% contained at a time. This
isolated the work area, and allowed
pedestrian traffic to flow. Dalco then
removed the failed bridge deck
coating via induction heat coating
removal equipment. The steel deck
was then prepared with shot blast
technology. Client specified the PPG
system consisting of Amerlock 2
primer and SFT650 Poly Urethane;
providing a durable, non-slip surface.
Date / Duration: July-Oct 2016
Project Value: $450,000
Total Man Hours: 4000